Balcony Repair in Cammeray: A Class 2 Duplex Rebuilt Across Every Level
Balcony repair on this 1940s Cammeray duplex meant rebuilding failed sub-floors across several tiers, alongside new windows and doors and a full repaint.
The building is a 1940s Class 2 duplex with two households. We ran the balcony reconstruction, the window and door replacement and the exterior repaint as one project, so both households shared the scaffolding and the project management.
Project at a glance
Location
Cammeray, Sydney
Building
1940s Class 2 duplex, two households
Work
Balcony reconstruction and waterproofing, window and door replacement, render repair and repainting
Client
The co-owners of both levels
The problem: leaking balconies and a building that needed to meet current fire rules
The balconies were the first problem. The timber sub-floors on several tiers had deteriorated and the balconies were leaking, which put the levels below at risk. The work had to be sequenced so the lower levels stayed protected while the upper ones were opened up.
The second was fire safety. The windows and doors were degraded and did not meet current requirements for a building this close to its boundary, so replacing them meant design changes to the approved plans.
The third was access. The site is small, so scaffolding and protection of the structure had to be planned before anything came off.


Replacing the windows and doors to meet fire-safety requirements
We removed and disposed of the old windows and doors on every level and replaced them with commercial-grade aluminium units, matched to the architectural plans, the window schedule and the BASIX certificate.
Fire-safety requirements for the boundary meant design modifications, and stainless steel mesh screens were supplied and installed where they called for them. Those variations were managed through the Private Certifier and the project’s structural engineering inspections, and the building reached its Construction Certificate and Occupation Certificate.

Rebuilding the balconies from the sub-floor up
The old timber decking came off and we repaired the failing sub-floor drainage underneath. Where the structure needed it, aluminium floor joists replaced the timber, and compressed fibre cement sheeting went over them. A multi-layer waterproofing membrane system followed, installed in accordance with the relevant Australian Standards.



The floor levels on the upper and ground balconies were raised to give a flush threshold at the door. That removes a trip hazard and stops water pooling against the doorway. Both main balconies were finished with outdoor tiles on a sand and cement bed.
The old balustrades were replaced with frameless glass panels, fixed to a structural engineer’s plan across the levels. The lower deck was refreshed and its timber repainted rather than replaced. If your own balconies are leaking, our balcony waterproofing page explains how we find the source before choosing a repair.
Repairing the render and repainting the exterior
To bring the two halves of the building together, the damaged render was patched and repaired to match the original character of the building. A three coat paint system went on the walls, and the gutters and fascias were prepared and painted to finish the roofline.

Managing two households as one project
Because the co-owners shared scaffolding and project management, the work ran as a single project rather than two. One programme covered the balconies, the windows and the repaint, with the certifier and engineer coordinated through us. Our Class 2 compliance page sets out the obligations that sit behind work like this.
Warranties
The work carries statutory warranties under the Home Building Act: six years on major defects, waterproofing included, and two years on everything else, from completion.
6 years
On major defects, waterproofing included, under the Home Building Act, from completion.
2 years
On everything else, from completion.
Class 2 Builder Sydney is the trading name of Sydney Building & Construction Group Pty Ltd, Licence No. 283692C.
Planning balcony or facade work on a Class 2 building?
Tell us the building, what you can see and what the committee has been told so far. We will inspect, explain what the work involves and send a written scope. Request a site inspection.