Basement Waterproofing in Turramurra: Excavating to the Footings and Lining the Inside

Basement waterproofing at this Turramurra property meant digging 3 metres down to the footings to waterproof and drain the outside of the walls, then lining the inside.

Trench excavated along the external wall of the Turramurra property during the basement project, with stormwater pipes laid, from the project timelapse
Trench excavated along the external wall of the Turramurra property during the basement project, with stormwater pipes laid, from the project timelapse

The property was two residential dwellings sharing a common basement. The basement was 3 metres deep and had been taking in water for decades. We managed the engineering, the excavation, the structural repair, the external waterproofing and drainage, the stormwater and the internal lining as one project. A timelapse of the work is below.

Project at a glance

Location

Turramurra, Sydney

Problem

Water entering a 3 metre deep basement over several decades

Work

Engineering, excavation, structural repair, external waterproofing, drainage, internal lining and stormwater

Approval

Planned under exempt development provisions

The problem: water pressing on a 3 metre wall

The basement walls were concrete block, 3 metres deep, and the ground around them stayed wet. Water in soil pushes on a wall for as long as the soil stays saturated, and that pressure drove moisture through the blockwork. Over decades it had damaged the concrete footings, loosened the mortar joints and degraded the surface of the internal walls and floor.


The stormwater system was part of the cause. The downpipes, the old pits and an oversized rainwater tank sent water into the ground beside the building during heavy rain, instead of away from it. Fixing only the inside of the basement would have left that water arriving at the wall.

Engineering and approvals before digging

Before any excavation, three things were settled:


A boundary survey, so a trench 3 metres deep stayed inside the property and clear of council easements.


A structural engineer’s assessment of how the building’s load reached the footings, to approve trenching beside them.


Civil drainage plans to redesign the stormwater, including a slimline rainwater tank to replace the old one.

The work was planned to fit within exempt development, so no development application was needed. We managed the trades and the safety controls around the open trench as the project manager.

Excavating 3 metres beside the footings

The trench was cut to the depth of the footings and kept narrow, 500 to 600 millimetres wide, to keep the ground stable. Concrete pathways and part of the driveway were saw cut first to keep clean edges.


Because live services can sit unmapped beside a building, we used hydro excavation, which removes soil with pressurised water and vacuum, along with hand digging in tight spots. Diamond core drills cut clean openings through the basement walls for the new drainage and services. Spoil and slurry were removed from site as the work went on.

Repairing the structure before waterproofing it

Waterproofing only lasts on a sound surface, so the repairs came first. Spalled concrete on the footings and slab edges was cut back to sound material, treated against corrosion and rebuilt with structural repair mortar. Failed mortar joints in the block walls were ground out and repointed. Inside, the walls were sandblasted to remove failed paint and salt deposits, and the floor was ground so the next layer would bond. This is the same approach we describe for concrete cancer repair.

Waterproofing and draining the outside

A fluid-applied waterproofing membrane went onto the repaired external walls and over the footings. A dimpled drainage cell was fixed over it to protect the membrane and carry water down the wall, and a slotted agricultural pipe wrapped in filter fabric took it away at the base. The trench was backfilled with 10 millimetre aggregate so water drains to the pipe instead of sitting against the wall.


Four new downpipes were connected to new stormwater lines and pits, and routed to the new slimline rainwater tank. Licensed plumbers did that work.

Lining the inside and finishing

With the water managed outside, an independent metal-framed wall was built inside the blockwork, standing clear of it, so a cavity separates the finished wall from the damp-proofed masonry. It was lined with 13 millimetre water-resistant plasterboard and finished with anti-mould paint. A storage room was waterproofed separately, and a licensed electrician reconnected the power points, lights and switches on the new walls.


The concrete aprons were re-poured to shed water away from the building, and the garden beds and plants were replaced to match what was there before.

What this project shows

Water entering a deep basement can have more than one cause. Here it was ground water, a failed wall and a stormwater system that fed the problem, and the repair dealt with all three in sequence. Our post on basement remediation explains how we find the source before choosing a method.

Warranties

The work carries statutory warranties under the Home Building Act: six years on major defects, waterproofing included, and two years on everything else, from completion.

6 years

On major defects, waterproofing included, under the Home Building Act, from completion.

2 years

On everything else, from completion.

Class 2 Builder Sydney is the trading name of Sydney Building & Construction Group Pty Ltd, Licence No. 283692C.

Planning basement waterproofing?

Tell us the building, where the water shows and how long it has been happening. We will inspect, trace the source and send a written scope. Request a site inspection.